It is reported that the Tianma (Wuhu) new display production line project has a total investment of 8 billion yuan. It was launched in May last year and officially started in November of the same year. The overall project lasted 121 days and the project closure was completed 60 days ahead of schedule<<. At present, the construction work of the project is progressing smoothly, and the equipment move-in work is expected to start in the second half of this year.
This project is mainly aimed at the three major application markets of vehicle display, IT display (tablets, laptops, monitors, etc.), and industrial product display. It will be fully connected with the Tianma panel production line. It is planned to be mass-produced in 2024 and fully produced in 2027. After full production, the planned monthly production capacity is 5.2 million display modules, with an annual output value of approximately 12 billion yuan. (Source: Tianma)